Coral Gables City Hall is the historic municipal building at 405 Biltmore Way in Coral Gables. Completed in 1928, the three-story landmark forms part of the city’s Mediterranean-inspired civic landscape. Its history includes changes to the commission chamber and interior decoration, followed by a major restoration programme announced in 2026.[3][1]
Civic architecture and interior change§
The Historic American Buildings Survey’s written record identifies Phineas Paist, Denman Fink and Harold Steward with the design. It places City Hall within the same civic architectural history as Douglas Entrance. The record describes native quarry keystone, stucco, a rotunda and a garden courtyard.[1]
The report, prepared by historian Carol R. Alper in 1981, records changes to the commission chamber in 1956. It also describes John St. John’s Landmarks of the Twenties mural and his 1957 restoration of Fink’s belltower painting. These are separate painted interventions, not interchangeable titles for one mural.[1]
Moving the commission in 2026§
A February 26, 2026 Coral Gables Gazette report records the commission’s final meeting in the historic chambers on February 24 before its restoration-related departure. The article announced a new meeting location at the Public Safety Building on Salzedo Street beginning in March, while describing separate temporary locations for administrative staff and commission offices.[2]
That report’s construction programme anticipated permits in June and work beginning in July, with completion targeted for December 2027. These were forecast dates when published, distinct from the commission’s already completed meeting. The relocation concerned municipal operations, rather than a new institution replacing the historic City Hall.[2]
Restoration design and later timetable§
Abraham Galvan’s October 7, 2026 Miami Today account identifies R.J. Heisenbottle Architects as the restoration designer. It describes plans for the city manager and clerk on the first floor, elected officials and the commission chamber on the second, and other administrative uses on the mezzanine and third floor.[3]
The October article scheduled construction to begin that month, later than the July start projected in the February report. It also described a planned perimeter fence carrying images of the proposed restored building. The successive reports document an evolving project timetable in Coral Gables, without establishing that construction or the full restoration had been completed by either publication date.[3][2]
Sources & references
- Written historical record, selected pages Historic American Buildings Survey / Carol R. Alper. Retrieved . ↑1↑2↑3
- Commission relocation — February 26, 2026 Coral Gables Gazette. Retrieved . ↑1↑2↑3
- Restoration programme — October 7, 2026 Miami Today / Abraham Galvan. Retrieved . ↑1↑2↑3